No due date, still a deadline
The customer FAQ has no date of its own. It gates the launch, so it inherits the launch’s date and its buffer is measured against that.
Drag a bar and watch what it does to the deadline of everything downstream. Gantt and advanced scheduling come with Individual and Business; the model below is a sample you can move.
Pick any task in the panel to see what it waits on, what waits on it, and what one lost day would do to the launch.
Prepare the fulfillment plan waits on Finalize the launch date. Run the dress rehearsal waits on it.
One lost day here moves 2 downstream tasks and the launch by 1 day. It is on the critical path.
Drag a bar, or use the arrow keys on it, to change how long a task takes. Everything downstream re-plans and the buffer recolours. Durations here are calendar days; the app forecasts from your estimates and working hours.
Buffer is the time between when a task can realistically finish and when it actually has to, measured against the deadline that truly binds it, which is often not its own.
Launch still lands by Sep 22, with 2 days to spare.
The customer FAQ has no date of its own. It gates the launch, so it inherits the launch’s date and its buffer is measured against that.
Slip one upstream task and every gap downstream narrows without anyone editing a bar. When a gap hits zero the task is critical; past zero, the plan is behind.
Forecasts there use your recorded estimates, working hours and recent velocity. Drag a bar to pin a start date and the timeline warns if a pinned task starts before its blockers finish.